Formal approval for the procurement of construction works for the Transforming Cities Manvers Cycleway project at a contract value of £823,513.
Decision:
RECORD OF OFFICER EXECUTIVE DECISION
Date of Decision:
|
02/03/2023 |
Decision Maker: (Including Job Title)
|
Simon Moss Assistant Director of Regeneration and Environment |
Specific Delegation: (If any)
|
Contract Standing Orders; Section 41.2: In relation to their Directorates, each Strategic Director has a general power to make council contracts, including the power to determine select lists of tenderers, to accept tenders and to award contracts. This is subsequently delegated to Assistant Directors in the sub-scheme of delegation.
|
Brief Description of Decision:
|
Formal approval for the procurement of construction works for the Transforming Cities Manvers Cycleway project at a contract value of £823,513 |
Reasons for the Decision:
|
Approval of this decision will allow the award of the contract to complete the TCF Manvers Cycleway project as part of the wider Transforming Cities Funding delivery. |
Details of alternative options considered and rejected:
|
Option 1: Consideration was given to tendering as a wider package of works but this was unviable due to timescales.
Option 2: Use of the internal works delivery service was considered, but was ruled out due to programming constraints.
|
Conflicts of interest declared by any Executive Member consulted by the decision maker which relates to the decision: |
Not applicable |
Dispensations Granted: (If any)
|
Not Applicable |
Reports or parts of reports considered |
21-210 Tender Evaluation Report Mavers cycle route |
I certify that this is a true record of the executive decision in relation to
Signed by the Decision Maker Simon Moss
Dated: 7.3.23
Name: Simon Moss
Job Title: Assistant Director, Planning, Regeneration & Transport
Publication date: 08/03/2023
Date of decision: 02/03/2023