To award main works contract for the Rotherham Markets and Library redevelopment to Henry Boot Construction Ltd. from 25th March 2024 in line with the decision at Cabinet on 18 December 2023.
ROTHERHAM METROPOLITAN BOROUGH COUNCIL
RECORD OF OFFICER EXECUTIVE DECISION
Date of Decision: |
04/04/2024 |
Title: |
Rotherham Markets & Library main works award |
Decision Maker: (Including Job Title) |
Paul Woodcock Strategic Director of Regeneration & Environment |
Specific Delegation: (If any) |
Delegation to award the main works contract for the Markets and Library redevelopment, in consultation with the Cabinet Member for Jobs and Local Economy and Section 151 Officer.
- Cabinet Report 18th Dec 2023 refers.
Cabinet approved the plans for the Rotherham Markets and Library development at its meeting on the 18th December 2023.
At the same meeting the Cabinet delegated authority to the Strategic Director of Regeneration of Environment, in consultation with the S151 Officer and the Cabinet Member for Jobs and Local Economy, to award contract(s) for the works (Rotherham Markets and Library development) up to the values detailed in Appendix 2 of the relevant Cabinet report.
- Cabinet Report 18th March 2024 refers.
Final costs and associated budgets identified in Appendix 4 that provide final parameters for award of said contract.
Cabinet Member consulted and in support – 03 April 2024 Section 151 Officer consulted and in support – 02 April 2024
|
Brief Description of Decision: |
The Council enters into contract with Henry Boot Construction Ltd for the delivery of the Markets and Libraries project. |
Reasons for the Decision: |
To maintain momentum behind the delivery programme of one of the Council’s key regeneration projects and ensure best possible value is secured.
|
Details of alternative options considered and rejected: |
The alternative option is not to sign the main works contract prepared. This option is not recommended, because it will not secure the commitment of Henry Boots Construction Ltd to deliver the scheme to an agreed specification for an agreed price in line with the approach adopted by the Cabinet |
Conflicts of interest declared by any Executive Member consulted by the decision maker which relates to the decision: |
None identified. |
Dispensations Granted: (If any) |
None
|
Reports or parts of reports considered |
Cabinet Report 18 December 2023 Cabinet Report 18 March 2024 |
I certify that this is a true record of the executive decision to agree to enter into contract with Henry Boot Construction Ltd for the delivery of the Markets and Libraries project.
Signed by the Decision Maker
Dated: 4th April, 2024
Name: Paul Woodcock
Job Title: Strategic Director, Regeneration & Environment
Publication date: 05/04/2024
Date of decision: 04/04/2024
Accompanying Documents: