Decision details

Acquisition of Plot 6, Laughton Road, Dinnington

Decision Maker: Strategic Director of Regeneration and Environment

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: No

Purpose:

Utilising the Assistant Director for Planning, Regeneration & Transport delegated authority to approve the acquisition of land interests to help facilitate the Dinnington High Street/Market scheme.

This is in accordance with the delegation given at Cabinet in August 2023 (minute no. 39/4 refers)

 

Decision:

ROTHERHAM METROPOLITAN BOROUGH COUNCIL

 

RECORD OF OFFICER EXECUTIVE DECISION

 

Date of Decision:

18th September 2024

Title:

Council acquisition of Plot 6, Dinnington, as part of the Strategic Land Acquisition for the Dinnington Market Site Regeneration Project

 

Decision Maker:

(Including Job Title)

Simon Moss

Assistant Director for Planning, Regeneration & Transport

 

Specific Delegation:

(If any)

Cabinet 07/08/2023 – Minute No. 39 / 4 – Approved that the Assistant Director for Planning, Regeneration and Transport be authorised to negotiate and agree the acquisition by agreement of the property interests at exempt Appendix 1, in consultation with the Council’s Section 151 Officer and the Cabinet Member for Jobs and the Local Economy.

 

Brief Description of Decision:

Assistant Director for Planning, Regeneration and Transport to approve the acquisition of Plot 6, Dinnington (shown on the plan attached at Appendix 2).

 

Reasons for the Decision:

Plot 6 forms a component of the land assembly necessary to facilitate the regeneration initiative planned for the Dinnington Markets area. The Council has commenced a programme of acquisitions to secure and bring under Council control the land necessary to enable the proposed development to take place. The completed development will create a new town square that will house a pop-up market, create new retail units and a community building, as well as enhance links between the bus interchange and car parks that serve the town centre. 

 

Details of alternative options considered and rejected:

Option 1 – Purchase by agreement. This is the preferred route and is the one sought by this Executive Decision.

 

Option 2 – Acquire via Compulsorily Purchase Order (CPO). The cabinet resolution noted above did approve the exploration of CPO powers. However, as required by Government guidance, acquisition by negotiation rather than the use of Compulsory Purchase powers is always preferable. This option can be dismissed in favour of acquisition by agreement. This option has therefore been rejected.

 

Option 3 – Do nothing, the acquisition is critical and necessary for the full regeneration ambitions for the Dinnington Markets area to be implemented. The plans have on the 13th September secured planning consent, and the scheme is widely supported by the local community and key stakeholders. This option has therefore been rejected.

Conflicts of interest declared by any Executive Member consulted by the decision maker which relates to the decision:

None

Dispensations Granted:

(If any)

None

 

Reports or parts of reports considered

 

None

 

 

I certify that this is a true record of the executive decision to approve the acquisition of Plot 6, Dinnington

 

Signed by the Decision Maker  

Dated: 18th September, 2024      

 

Name: Simon Moss                             

Job Title: Assistant Director, Planning, Regeneration & Transport

 

 

Publication date: 19/09/2024

Date of decision: 18/09/2024