Decision Maker: Executive Director of Regeneration and Environment
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: No
The Strategic Director Regeneration and Environment to approve the Tender evaluation report and support the award the Engineering & Construction Contract to deliver the Whiston Brook Flood Alleviation Scheme. Contract award notice will be published the Council’s Contracts register and on Contracts Finder and Find a Tender.

ROTHERHAM METROPOLITAN BOROUGH COUNCIL
RECORD OF OFFICER EXECUTIVE DECISION
|
Date of Decision: |
23rd December, 2025
|
|
Title: |
Whiston Brook Flood Alleviation Scheme - Contractor Procurement - Contract Award |
|
Decision Maker: (Including Job Title) |
Sam Barstow – Assistant Director Community Safety and Street scene
|
|
Details of Specific Delegation
or
Delegation contained in the relevant Sub-Scheme of Delegation.
|
Delegated powers to Assistant Director of Community Safety and Street Scene:
Sub Scheme of Delegation - Strategic Director of Regeneration and Environment
Page 3 refers:
Each to act in relation to matters within their remit unless absent in which case any other Assistant Director may act …
3. In respect of procurement, contract administration and best value:
In accordance with Financial and Procurement Procedure Rules, matters relating to the specification for works, goods and services, the seeking of estimates, quotations and tenders, the evaluation of the same and acceptance of tenders relating to contracts for works, goods and services in accordance with approved budgets or supplementary estimates.
|
|
Decision: |
To approve the tender exercise 22-197 to appoint an external contractor to carry out the construction of Whiston Brook Flood Alleviation Scheme (FAS). Scheme estimated value of £4.2 million
|
|
Reasons for the Decision: |
To allow Highways and Flood Service to progress the delivery of the Whiston FAS.
|
|
Details of alternative options considered and rejected: |
No alternative options considered.
No capacity to use inhouse team for construction due to the scale and specialist nature of the work |
|
Conflicts of interest declared by any Cabinet Member consulted by the decision maker which relates to the decision: |
None |
|
Dispensations Granted: (If any) |
None |
|
Conflicts of interest declared by the Decision Maker if they sit as a Cabinet appointed representative to an outside body which relates to the decision: |
None |
|
Dispensations Granted: (If any) |
None.
|
|
Reports or parts of reports relevant to the decision being taken:
|
Procurement Business Case 22-197 Whiston Brook Flood Alleviation Scheme Works only – exempt.
Tender Evaluation Report 24-197 Whiston Brook Flood Alleviation Scheme – exempt. |
I certify that this is a true record of the executive decision to:
To approve the tender exercise 22-197 to appoint an external contractor to carry out the construction of Whiston Brook Flood Alleviation Scheme (FAS) with an estimate scheme value of £4.2 million.
I confirm that in making this decision, due regard was given to the seven principles of public life.
Signed by the Decision Maker:
![]()
Dated: 23rd December, 2025
Name: Sam Barstow
Job Title: Assistant Director, Community Safety & Street Scene
Publication date: 23/02/2026
Date of decision: 23/12/2025