Decision details

(R&E) YORbuild2 Framework - Extension

Decision Maker: Strategic Director of Regeneration and Environment

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

To extend the YORbuild2 South Area Contractors Framework Agreement for a further 2 years.

Decision:

 

ROTHERHAM METROPOLITAN BOROUGH COUNCIL

 

RECORD OF OFFICER EXECUTIVE DECISION

 

Date of Decision:

 

30 April 2019

Decision Maker:

(Including Job Title)

 

Paul Woodcock

Strategic Director of Regeneration and Environment

Specific Delegation:

(If any)

 

Financial and Procurement Procedure Rules

Section 58.4 Delegation Arrangements.

Brief Description of Decision:

 

 

That the Strategic Director of Regeneration and Environment authorises, in line with Financial and Procurement Procedure Rule Section 58.4 Delegation Arrangements, the proposal to extend the YORbuild2 South Area Contractors Framework Agreement for a further 2 years.

 

Reasons for the Decision:

 

The framework is due to expire in February 2020 unless the option to extend for a further 2 years is taken.

Details of alternative options considered and rejected:

 

1.     Terminate the framework after 4 years which was rejected because:-

·      Appointed Contractors and users don’t recoup their investments

·      The Council would need to start gearing up to replace the framework at a time when two new frameworks are planned due to unexpected high levels of demand for major projects.

·      To renew the YORbuild2 framework is estimated to cost £250,000 and would tie up procurement staff for a duration of 12 months. 

·      Momentum would be lost in delivering initiatives such as Employment and Skills.

 

Conflicts of interest declared by any Executive Member consulted by the decision maker which relates to the decision:

None

Dispensations Granted:

(If any)

 

None

Reports or parts of reports considered

 

Report to Strategic Director of Regeneration and Environment 17 June 2019.

 

 

I certify that this is a true record of the executive decision in relation to the proposal to extend the YORbuild2 South Area Contractors Framework Agreement for a further 2 years.

 

Signed by the Decision Maker                                          Dated 17 June 2019

Paul Woodcock

Name          Paul Woodcock

Job Title      Strategic Director of Regeneration & Environment

 

Publication date: 17/06/2019

Date of decision: 17/06/2019