Decision Maker: Strategic Director of Finance and Customer Services
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: No
To appoint contractor for RIBA Stage 4 designs of Wath Library Redevelopment.
ROTHERHAM METROPOLITAN BOROUGH COUNCIL
RECORD OF OFFICER EXECUTIVE DECISION
Date of Decision: |
7th April, 2025
|
Title: |
Award of PCSA Contract for the new Wath Library redevelopment
|
Decision Maker: (Including Job Title) |
Kevin Fisher, Assistant Director for Property and Facilities Services
|
Details of Specific Cabinet Delegation or Delegation contained in the relevant Sub-Scheme of Delegation.
|
In accordance with Appendix 5 on the Constitution – Financial and Procurement Procedure Rules, Section 42 onwards for specific powers delegated to the Property Officer.
Noting Cabinet’s authorisation on two separate occasions, namely:-
10 July 2023 – “That Cabinet delegate the Commissioning of the design of the project ….. to the Strategic Director for Regeneration and the Environment in Consultation with the Cabinet Member for Jobs and the Economy and the Section 151 Officer”.
And 29 July 2024 – “The delivery of the Wath Principal Areas of Growth project within the budget and scope as detailed in Appendix 2 (restricted)”
|
Decision: |
An outcome is to recommend award of the Stage 1 Pre-construction contract to Tilbury Douglas following a competitive tendering exercise.
|
Reasons for the Decision: |
This scheme consists of a two-stage design and build contract, this is the award of the stage 1 Pre-contract Service Agreement awarded to Tilbury Douglas to undertake the Stage 4 design onwards prior to seeking approval to undertaking the Stage 2 construction contract.
|
Details of alternative options considered and rejected: |
None |
Conflicts of interest declared by any Cabinet Member consulted by the decision maker which relates to the decision: |
None declared. |
Dispensations Granted: (If any) |
N/A
|
Reports or parts of reports considered |
Cabinet in August 2023 Cabinet in July 2024 |
I certify that this is a true record of the executive decision to ….
To award a Construction contract to Tilbury Douglas in relation to the redevelopment of Wath Library.
Signed by the Decision Maker
Dated: 7th April 2005
Name: Kevin Fisher
Job Title: Assistant Director, Property and Facilities Services
Publication date: 14/04/2025
Date of decision: 07/04/2025
Accompanying Documents: