Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
To consider the initial response received to
the development brief, signing off of full development brief and
approve requirements for the site
Consideration was given to the report which provided an update on progress following the market testing of a redevelopment opportunity for two sites one a vacant Council owned site proposed for residential development and the other the existing Council buildings in Swinton Town Centre.
The site was fronted by Council owned retail and residential units and community facilities, the rear of the site was vacant. The vacant element was suitable for housing and the development of this land offered the opportunity to bring forward improvements to the Council owned assets. This report also requested the approval required to progress this project through the submission of a Development Brief to the open market.
Resolved:- (1) That aims and objectives for the redevelopment of Swinton Town Centre as set out at section 2 of this report be approved.
(2) That an OJEU compliant procurement process be approved to be undertaken in accordance with Rotherham Council’s Contract Procedure Rules and Domestic and European Procurement Law.
(3) That Option 2 be approved as set out at paragraph 4.2 of the report. This option foregoes an amount of capital receipt to the Council in order to achieve regenerative benefits to the Community and the Council in relation to the redevelopment.
(4) That a further report be submitted following the evaluation of the tender submissions received, which recommends the endorsement of the preferred proposal and any approvals required for the disposal of land and property.
Publication date: 08/02/2019
Date of decision: 17/12/2018
Decided at meeting: 17/12/2018 - Cabinet
Effective from: 01/01/2019
Accompanying Documents: