Housing Market Renewal Pathfinder Financial Monitoring

Meeting: 01/08/2007 - Housing Market Renewal Pathfinder (Item 10)

Housing Market Renewal Pathfinder Financial Monitoring

- report by Joel Gouget, Finance Manager

Minutes:

Joel Gouget, Finance Manager, submitted the financial monitoring of the Pathfinder Programme in 2006/07 as at the end of May, 2007.

 

As at the end of March, 2007, the Programme had delivered £7.6M of investment and achieved spend and delivery targets set for the 2006/07 period.  The current spending plan was set to deliver an additional £10.6M of interventions by the end of March, 2008.

 

Risks on the Westgate Demonstrator were closely monitored.

 

A short powerpoint presentation was given on accelerated projects to pick up any shortfall on strategic acquisitions and in the town centre.

 

Agreed:-  (1)  That the report be noted.

 

(2)  That a further report be submitted to the September meeting.


Meeting: 19/03/2007 - Housing Market Renewal Pathfinder (Item 136)

Housing Market Renewal Pathfinder Financial Monitoring

Minutes:

Joel Gouget, Finance Manager, submitted the financial monitoring of the Pathfinder Programme in 2006/07 as at the end of February, 2007.

 

The investment programme approved by TSY was £6.9M with expenditure to date of £5.4M and committed expenditure of £1.5M.  In addition, Rotherham was pursuing additional expenditure of £0.9M related to acquisitions, bringing the total spend for 2006/07 to £7.8M.

 

At the end of February, 2007, the overall risk to deliver the Programme was rated low as the projects scheduled to be delivered exceeded the HMR Pathfinder allocation.

 

Agreed:-  (1)  That the report be noted.

 

(2)  That further reports be submitted at agreed intervals.