Meeting: 01/08/2007 - Housing Market Renewal Pathfinder (Item 5)

Brampton Neighbourhood Masterplan

- presentation by Barry Deakin, HMR Manager

Minutes:

Barry Deakin, HMR Manager, gave a powerpoint presentation on the 3 key concepts identified by the consultants:-

 

Communicating with DearneValley

Sustainable living

Finding a new Village focus

 

Emerging from the consultation that had been carried out:-

 

-              Identifying Delivery Champion

-              Housing stock condition survey

-              HMR activity

-              Issues surrounding the fire station site

-              Village Green concept

-              Supporting gateways and Cortonwood connections

 

Deliverable 1

-              Appointing a senior officer for delivery of the masterplan

-              Benefits of post

-              Set agenda

-              Preliminary activity and driving the change

 

Deliverable 2

-              Stock condition survey

 

Deliverable 3

-              Fire station site

 

Deliverable 4

-              The Village Green

 

Deliverable 5

-              Gateways

 

Deliverable 6

-              Cortonwood Connections

 

Next Steps

-              Final consultations with Programme Areas and partners – July, 2007

-              Presentation to the Brampton Sub-Group – August, 2007

-              Formal sign off with Wath and Swinton Steering Group – August, 2007

-              Report to Cabinet Members – September, 2007

-              Formal Project Team to look at developing the Deliverables – September, 2007

 