Further to Minute No. 61 Chrissy Wright, Strategic Commissioning Manager, presented the revised version of the JSNA taking account of the representations received.

 

The 6 weeks consultation with stakeholders had run between 30th December, 2013 and 9th February, 2014.  Details of the draft JSNA website had been circulated to a range of stakeholders, both statutory and VCS agencies, as well as a well attended VCS consultation session held on 27th January.

 

The consultation had been generally positive.  Comments and suggestions made were constructive and would help to develop the JSNA.

 

A new requirement was to include a register of community assets which would be developed in 2014 with progress reported in JSNA updates.

 

It was noted that the document had now been “signed off”.  However, in future “sign off” would be in line with commissioning priorities and planning.

 

Resolved:-  (1)  That the current version of the Rotherham Joint Strategic Needs Assessment, updated following consultation, be approved.

 

(2)  That quarterly reports of any significant changes or otherwise by exception be submitted to the Board.