Report from the Executive Director of Regeneration and Environment.
Recommendations:
That Cabinet note:
2.
The planned April–October gateway cleansing and maintenance
programme and the improved data capture now in place to inform
future scheduling.
Minutes:
Consideration was
given to the report which provided a progress update on rural verge
cleansing, outlined the forthcoming gateway maintenance programme,
and noted the agreed development of a second Rural Verge &
Principal Gateway Cleansing and Maintenance (RVGC) team. In March
2025, Council had approved a £307k investment to create the
new team to improve the cleanliness and appearance of rural verges
and key gateway locations across the Borough. Following recruitment
and traffic management (TM) training, the Team became fully
operational in October 2025.
Headlines to date (since mobilisation):
· 117 sites completed (133 remaining, targeted for completion by the end of March 2026.)
· 146 km of roadside verge litter-picked.
· 4,200 bags of waste removed and 12 tonnes collected, plus additional tonnage from several large fly-tipping jobs.
·
Data capture enhanced: daily bag counts, weights, and hotspot
intelligence (flytipping, asbestos, drug paraphernalia) now
recorded to inform future schedules and enforcement.
From late March/early
April the RVGC team would switch to the gateway programme, while
the established verge team commenced its May–October cycle.
The gateway work was a new scheduled activity covering several key
routes in and out of the borough. The scope included detritus
removal, weed treatment/clearance, litter-picking, removal of
overhanging branches/hedges, grubbing out, and other tasks needed
to improve gateway appearance. Officers would monitor progress,
recognising that some locations might require a return visit to
complete the full scope of works required. This programme was in
addition to any routine jobs logged by residents in these
areas.
In March 2026, Council approved a further revenue investment of
£272k to create a second RVGC team. Recruitment commenced in
mid-March 2026 and a full-year update on both teams’
performance would be reported in April 2027.
Resolved:
That Cabinet
note:
1.
The progress delivered by the RVGC team since
mobilisation.
2. The planned April–October gateway cleansing and maintenance programme and the improved data capture now in place to inform future scheduling.
Supporting documents: