Report from the Strategic Director of Children and Young People’s Services.
Recommendations
That Cabinet:
1. Note the activity undertaken and progress to date on SEND Sufficiency Phase 4.
2. Note the key outcomes for SEND Sufficiency Phase 5 as included in the Safety Valve Agreement and agree for an additional paper to return to Cabinet once an initial feasibility has been completed.
Minutes:
Consideration was
given to the report which provided an update in respect of Special
Educational Need or Disability (SEND) Sufficiency following the
update received by Cabinet in June 2023. The report also detailed
the key activities undertaken in implementing Phase 4 of the SEND
Sufficiency programme focusing on resource provision development
and roll out of the Schools’ Accessibility Funding Programme
across both mainstream and special schools. The report also
identified key activities and outcomes that were currently in the
process of development as part of a further Phase 5 SEND
Sufficiency linked to the Safety Valve Agreement.
From 2018 onwards, Cabinet had approved four previous Phases of
SEND
Sufficiency, each
targeted at addressing incremental rises in SEND cohorts and
creating or improving specialist education provision. The first
three Phases of the SEND Sufficiency programme had created 401
additional school places in Rotherham. A further breakdown of the
different Phases was set out in paragraph 1.5 of the report.
Phase 4 of the programme was approved for implementation in June
2023 with the main aim of SEND Sufficiency Phase 4 to support
mainstream schools to meet a wider level of need and improve
accessibility within both mainstream and special schools. Phase 4
included the development of a
minimum of 10 resource provisions across mainstream settings creating 100
new SEND places. A second main aim of SEND Sufficiency Phase 4 was
the implementation of the Schools’ Accessibility Funding Framework across
both mainstream and
special schools.
Following the expression of interest process and due diligence, the
first Phase of resource provision implementation took place in
Spring Term 2023. This included the approval of new resource
provision at Thrybergh Academy and
Dalton Foljambe and
additional places at Wales High School resource provision. It was
anticipated the building works would be completed so that the first
places for children were available in September 2024. There were
currently 5 schools working through approvals to support the
opening of their resource provision. Further details were provided
a paragraph 2.1.3 of the report. Subject to completion of building
works and necessary DfE approvals, eight provisions for Phase 4
were scheduled to be completed by September 2024 with the
additional 100 places being delivered in a staged way over the
remaining two academic years.
In June 2023 Cabinet approved the School’s Accessibility
Strategy and Accessibility Capital Funding Framework. The intention
of Schools’ Accessibility Funding was to support schools to
meet a wider level of SEND need through adaptations to existing
buildings. Since the launch, funding had been awarded to the
following special schools: Nexus (Forest View) - £370k;
Newman School - £15k; and Elements Academy - £67k.
Paragraph 2.2.5 of the report set out the details of the approved
bids for the accessibility capital funding small grants’
programme.
The Safety Valve Agreement recognised a Phase 5 of SEND Sufficiency. The
main focus of Phase 5 was to provide increased sufficiency of places and
condition improvements within the specialist provision. Phase 5 would cover three core elements: Social, Emotional, and Mental Health (SEMH) growth; Newman School; and Pupil Referral Unit Development. Additional details of these elements were set out in paragraph 2.2.8 of the report. SEND Sufficiency Phase 5 projects were currently forming part of a feasibility study which would be completed during Spring Term 2024. The study would identify appropriate options for development including identifying appropriate school
assets which could be developed, capital investment required and timescales
for delivery. On completion of the feasibility study a further Cabinet report would seek appropriate approval to implement Phase 5.
Resolved:-
That Cabinet:
1. Note the activity undertaken and progress to date on SEND Sufficiency Phase 4.
2.
Note the key outcomes for SEND Sufficiency Phase 5 as included in
the Safety Valve Agreement and agree for an additional paper to
return to Cabinet once an initial feasibility has been
completed.
Supporting documents: