Report from the Strategic Director of Adult Care, Housing and Public Health.
Recommendations:
That Cabinet:
1.
Approves the newly identified Council-owned site
listed in Appendix 1 being brought forward to deliver new Council
homes.
2.
Approves the removal of Mill Lane, South Anston from
the Housing Delivery Programme as listed in Appendix 1.
3.
Approves the disposal of Mill Lane, South Anston via
open market sale or auction.
5.
Approves the purchase of homes from any of the
schemes identified in Exempt Appendix 2.
6.
Notes that authority to purchase up to 100 homes
from the market has been delegated to the Assistant Director for
Housing following approval of the Housing Acquisitions Policy
Cabinet report on 16 October 2023. The 100 homes provision is now
reflected in Exempt Appendix 2.
7. Agrees to continue to receive an update on the housing development programme every six months.
Minutes:
Consideration was
given to the report which provided an update on the Housing
Delivery Programme, summarising progress since the previous
programme report was approved by Cabinet in January 2024. There
were several changes required to the programme which required
renewed approvals from Cabinet.
Overall, from 1 January 2018 to 31 May 2024, the Council had
successfully
delivered 565 new Council homes consisting of 430 homes for rent and 135
homes for shared
ownership. Of these new homes:
The Council had also built 125 new homes for market sale. An updated
photographic summary
of delivery was provided at Appendix 3. Paragraphs 1.6 to 1.9 of
the report detailed the progress made since December 2023.
As of 31 May 2024, the Council was in contract to deliver a further
85 homes
with an estimated 60 homes for rent and 3 for shared ownership expected to be completed by March 2026. This means a cumulative total of 621 Council
homes were already complete or contracted for completion by March 2026.
This excluded homes built for market sale and homes which were due to be
delivered after March
2026. The latest programme position was summarised is paragraph
1.11 of the report with further detail provided in Appendix 1 and
Exempt Appendix 2.
The changes to the programme were outlined in paragraph 1.13 of the
report. These included the addition of a Council-owned site, The
Lanes at East Dene (estimated 2 homes); the removal of a
Council-owned site, Mill Lane at South Anston (estimated 3 homes);
the addition of nine schemes through strategic acquisitions
(estimated 139 homes) and the removal of two strategic acquisition
schemes (estimated 34 homes.)
Following site investigations and internal conversations, the
decision had been made to propose the removal of Mill Lane from the
Programme due to
the known site
constraints and high indicative costs for build. The Council would
look to dispose of the site through either open market sale or
auction (to be determined following valuations). The estimated site
value was just under the monetary threshold for Cabinet approval
however as it was close to the threshold, it could exceed the limit
that would require Cabinet approval. As this site had incurred
costs allocated for the Programme, it was proposed that the Capital
receipt from the disposal of the site be ringfenced and repurposed
on other sites within the Programme.
Councillor Allen highlighted the consultation details as set out in
section 4 of the report. The risks and mitigations were summarised
at paragraph 13.2.
Resolved:
That Cabinet:
Supporting documents: