ROTHERHAM METROPOLITAN BOROUGH COUNCIL
RECORD OF OFFICER EXECUTIVE DECISION
Date of Decision:
|
15 August 2018 |
Decision Maker: (Including Job Title)
|
Damien Wilson Strategic Director of Regeneration and Environment |
Specific Delegation: (If any)
|
None |
Brief Description of Decision:
|
That a delivery agreement is entered into with Balfour Beatty Group Ltd for the design and build works for the College Road Roundabout NPIF scheme, noting that the agreement contains a break clause after the design phase that allows the build works to be removed from the agreement.
|
Reasons for the Decision:
|
The report seeks authority to enter into a delivery agreement for the design and build works for the College Road Roundabout ‘NPIF’ scheme.
|
Details of alternative options considered and rejected:
|
The option of delivery by internal resources has been considered. However, due to the nature of the works, (which includes significant structural work to the existing subways and signal works), this option has been rejected due to the lack of internal resources in these areas to undertake a project of this size. Frameworks are the preferred method of procurement after internal delivery, due to the quick procurement process and the partnership working they encourage.
For this project, the ‘Scape Procure’ framework has been determined as the most appropriate, as it facilitates a design and build option, with early contractor involvement and project management by the nominated works contractor. This will be key to the delivery of the project if the tight timescales imposed by DfT are to be met. |
Conflicts of interest declared by any Executive Member consulted by the decision maker which relates to the decision: |
None |
Dispensations Granted: (If any)
|
None |
Reports or parts of reports considered
|
Report to Strategic Director of Regeneration and Environment 15 August 2018. Approval to enter into a delivery agreement to undertake the design and build works at College Road Roundabout ‘NPIF’ Scheme. |
I certify that this is a true record of the executive decision in relation to entering into a delivery agreement with Balfour Beatty Group Ltd for the design and build works for the College Road Roundabout NPIF scheme.
Date 16.08.2018
Name Damien Wilson
Job Title Strategic Director of Regeneration and Environment