Milton School - Classroom Extension for SEND

02/06/2020 - Milton School - Classroom Extension for SEND

ROTHERHAM METROPOLITAN BOROUGH COUNCIL

 

RECORD OF OFFICER EXECUTIVE DECISION

 

Date of Decision:

 

02/06/2020

Decision Maker:

(Including Job Title)

 

Paul Woodcock

Strategic Director of Regeneration & Environment

Specific Delegation:

(If any)

 

Appendix 5 of the Constitution - Financial and Procurement Procedure Rules

Section 41.2 Delegation Arrangements.

Brief Description of Decision:

 

 

To approve the tender submitted by O & P Construction to build a two classroom extension at Milton School.

Reasons for the Decision:

 

 

The procurement process was undertaken in order to identify a contractor to build a two classroom extension at Milton School to provide an additional 20 places for students with SEND.  This is part of the Council’s SEND Strategy to increase SEND places for children with autism spectrum conditions, moderate learning difficulties and social, emotional and mental health issues across Rotherham.

 

Details of alternative options considered and rejected:

 

The approved Children and Young People’s Service (CYPS) Capital Programme (approved at the Cabinet meeting on
16 September 2019), includes the Special Educational Needs and Disability (SEND) phase 2, with the works at Milton allocated £398,000.

 

The cost of these tendered works is £382,880, which can be contained within the approved budget, with the surplus £15,120 being added to the sub programme contingency.

 

Conflicts of interest declared by any Executive Member consulted by the decision maker which relates to the decision:

 

None

Dispensations Granted:

(If any)

 

N/A

Reports or parts of reports considered

 

Tender Report - 717/8/70 Milton School Classroom Extension for SEND

 

I certify that this is a true record of the executive decision to award the contract to O&P Construction for the work to build an extension at Milton School.

 

Signed by the Decision Maker  

Dated:            02/06/2020

 

Name:            Paul Woodcock                               

Job Title:      Strategic Director of Regeneration & Environment