Date of Decision:
|
02/06/2020 |
Decision Maker: (Including Job Title)
|
Paul Woodcock Strategic Director of Regeneration & Environment |
Specific Delegation: (If any)
|
Appendix 5 of the Constitution - Financial and Procurement Procedure Rules Section 41.2 Delegation Arrangements. |
Brief Description of Decision:
|
To approve the tender submitted by O & P Construction to build a two classroom extension at Milton School. |
Reasons for the Decision:
|
The procurement process was undertaken in order to identify a contractor to build a two classroom extension at Milton School to provide an additional 20 places for students with SEND. This is part of the Council’s SEND Strategy to increase SEND places for children with autism spectrum conditions, moderate learning difficulties and social, emotional and mental health issues across Rotherham.
|
Details of alternative options considered and rejected:
|
The approved Children and Young
People’s Service (CYPS) Capital Programme
(approved at the Cabinet meeting on
The cost of these tendered works is £382,880, which can be contained within the approved budget, with the surplus £15,120 being added to the sub programme contingency.
|
Conflicts of interest declared by any Executive Member consulted by the decision maker which relates to the decision:
|
None |
Dispensations Granted: (If any)
|
N/A |
Reports or parts of reports considered
|
Tender Report - 717/8/70 Milton School Classroom Extension for SEND |
I certify that this is a true record of the executive decision to award the contract to O&P Construction for the work to build an extension at Milton School.
Signed by the Decision Maker
Dated: 02/06/2020
Name: Paul Woodcock
Job Title: Strategic Director of Regeneration & Environment