RECORD OF OFFICER EXECUTIVE DECISION
Date of Decision: |
09/10/2023
|
Title: |
Surrender of lease - Substation in Riverside Gardens Public Realm
|
Decision Maker: (Including Job Title) |
Simon Moss Assistant Director, Planning, Regeneration & Transport Regeneration & Environment
|
Specific Delegation: (If any) |
The implementation of any functions associated with any grant regime, including National Grants, City Region Grants & Programmes and European Funding.
|
Brief Description of Decision: |
As part of the Riverside Gardens Public Realm scheme, it is necessary to remove the substation currently located within its boundary to enable levels to be created to provide an accessible route through the gardens. Northern Power decommissioned the substation in July 2023 and the surrender of the lease for land is being negotiated to enable its demolition.
The decision is to approve the surrender of the lease.
|
Reasons for the Decision: |
|
Details of alternative options considered and rejected: |
The approved designs for the scheme require the demolition of the substation to enable levels to be created to provide an accessible route through the gardens.
|
Conflicts of interest declared by any Executive Member consulted by the decision maker which relates to the decision: |
n/a |
Dispensations Granted: (If any) |
n/a
|
Reports or parts of reports considered |
n/a |
I certify that this is a true record of the executive decision to approve the surrender of lease - substation in Riverside Gardens public realm.
Signed by the Decision Maker
Dated: 09/10/23
Name: Simon Moss
Job Title: Assistant Director, Planning, Regeneration and Transport