1. Approval of the Full Business Case detailing final project costs, timeframe and outcomes, thus allowing contract award and implementation of the project.
2. To award the works contract on a fixed price basis using the NEC4 Option A in relation to the refurbishment of Thrybergh Country Park café and external landscape improvement works. As detailed in exempt Appendix 2 – Tender Evaluation Report.
Decision type: Key
Decision status: Recommendations Approved
Wards affected: Dalton & Thrybergh;
Notice of proposed decision first published: 08/11/2024
Anticipated restriction: Part exempt - View reasons
Open/Exempt: Exempt;
Decision due: June 2025 by Strategic Director of Regeneration and Environment
Lead director: Strategic Director of Regeneration and Environment
Department: Regeneration and Environment
Contact: Tanya Shvab, Project Manager Email: Tanya.Shvab@rotherham.gov.uk Email: Tanya.Shvab@rotherham.gov.uk, Matthew Stewart, Building Design Team Manager Email: matthew.stewart@rotherham.gov.uk.
Consultees
Relevant Members, Officers and Stakeholders.