Issue details

Request for temporary use of part of Boston Park by Yorkshire Water

To approve the use of around 8,800Sqm of Boston Park for a period of up to 2 years by Yorkshire Water for the storage of materials and site accommodation while rebuilding existing underground reservoirs on adjacent land owned by Yorkshire Water.

Decision type: Key

Decision status: Recommendations Approved

Wards affected: Boston Castle;

Open/Exempt: Open;

Decision due: 23 December 2019 by Cabinet

Lead member: Cabinet Member - Social Inclusion

Lead director: Strategic Director of Regeneration and Environment

Department: Regeneration and Environment

Consultees

Boston Castle Ward Members. Friends of Boston Park. Local Residents

Date Report and Background Papers will be available: 13 December 2019