Full Business Case: Templeborough Development; Funding Contribution agreement and Grant agreement: Magna & Rotherham Council; Main Works agreement: HBC Ltd. & Rotherham Council;

1.    To approve a Full Business Case detailing final Templeborough (Town Deal) project costs, timeframe and outcomes thus allowing a contract award and implementation of the project.

2.    To approve signing of a Funding Contribution agreement and a Grant agreement between Magna and the Council to enable the delivery of the Templeborough (Town Deal) project.

3.       To approve signing of a Main Works agreement between Henry Boot Construction Limited and the Council to enable the delivery of the Templeborough (Town Deal) project.

Decision type: Key

Decision status: For Determination

Wards affected: Boston Castle;

Notice of proposed decision first published: 07/06/2024

Anticipated restriction: Part exempt  - View reasons

Open/Exempt: Exempt;

Decision due: July 2024 by Strategic Director of Regeneration and Environment

Lead director: Strategic Director of Regeneration and Environment

Department: Regeneration and Environment

Contact: Lorna Vertigan, Strategic Regeneration Manager Email: lorna.vertigan@rotherham.gov.uk.

Consultees

Cabinet Member for Jobs & Local Economy

S151 Officer

Documents

  • Report and Appendices